The time limits for responding to a requirement for information under 37 CFR 1.105 are as follows:
- For a non-final Office action: The response period is typically two months, which may be extended up to six months from the Office action mailing date.
- For a final Office action: The response period is typically three months, which may be extended up to six months from the Office action mailing date.
As stated in MPEP 704.10: The time periods for reply to a requirement for information are set forth in 37 CFR 1.135(a). See also MPEP § 710.02(c).
It’s important to note that extensions of time may require additional fees and proper petitions.