Is there a deadline for filing the English translation and accuracy statement for a non-English provisional application?
Yes, there is a deadline for filing the English translation and accuracy statement for a non-English provisional application. While MPEP ¶ 2.38 doesn’t specify an exact timeframe, it indicates that the USPTO will set a time period in an Office action: “If 1) and 2) are not filed (or if the benefit claim is not…
Read MoreCan the English translation and accuracy statement be filed in the non-provisional application instead of the provisional?
No, the English translation and accuracy statement for a non-English provisional application cannot be filed in the non-provisional application. They must be filed in the provisional application itself. MPEP ¶ 2.38 is explicit about this requirement: “An English translation of the non-English language provisional application and a statement that the translation is accurate must be…
Read MoreHow do I properly claim the benefit of a prior application?
To properly claim the benefit of a prior application, you must include a specific reference to the prior application. For applications filed on or after September 16, 2012, this reference must be included in an application data sheet (ADS). For applications filed before September 16, 2012, the reference must be in an ADS and/or in…
Read MoreWhat is the time limit for submitting a benefit claim?
The time limit for submitting a benefit claim depends on the type of application: For utility or plant applications filed under 35 U.S.C. 111(a), the specific reference must be submitted during the pendency of the application and within the later of four months from the actual filing date of the application or sixteen months from…
Read MoreWhat happens if I miss the deadline for submitting a benefit claim?
If you miss the deadline for submitting a benefit claim, you may still be able to claim the benefit by filing a petition. According to MPEP 211.02: A benefit claim filed after the required time period may be accepted if it is accompanied by a grantable petition to accept an unintentionally delayed benefit claim under…
Read MoreHow do I correct or add a benefit claim after filing my application?
To correct or add a benefit claim after filing your application, you need to follow specific procedures depending on the timing and circumstances: If you received a filing receipt with missing or incorrect benefit claim information, you can request a corrected filing receipt. However, the Office will only grant this request if the proper reference…
Read MoreCan I delete a benefit claim, and what are the implications?
Yes, you can delete a benefit claim, but it’s important to understand the process and potential implications: For applications filed on or after September 16, 2012, you can delete a benefit claim by filing a corrected Application Data Sheet (ADS) that removes the reference to the prior-filed application. For applications filed before September 16, 2012,…
Read MoreHow do I claim the benefit of a prior-filed application?
To claim the benefit of a prior-filed application, you must include a specific reference to the prior-filed application in your current application. The method of including this reference depends on when your application was filed: For applications filed before September 16, 2012: Include the reference in the first sentence(s) of the specification following the title…
Read MoreWhat is the deadline for submitting a benefit claim?
The deadline for submitting a benefit claim depends on the type of application: For utility or plant applications filed under 35 U.S.C. 111(a): Submit within the later of four months from the actual filing date of the application or sixteen months from the filing date of the prior application. For national stage applications under 35…
Read MoreDo I need to file a petition if I submitted the benefit claim reference within the required time period but in the wrong location?
If you submitted the reference to the prior application within the required time period but in the wrong location, you may not need to file a petition. The MPEP provides guidance on this situation: If the reference to the prior application was previously submitted within the time period set forth in 37 CFR 1.78 but…
Read More