MPEP § 2692 — Distribution of Certificate (Annotated Rules)
§2692 Distribution of Certificate
This page consolidates and annotates all enforceable requirements under MPEP § 2692, including statutory authority, regulatory rules, examiner guidance, and practice notes. It is provided as guidance, with links to the ground truth sources. This is information only, it is not legal advice.
Distribution of Certificate
This section addresses Distribution of Certificate.
Key Rules
AIA Effective Dates
The Office does not accept requests for inter partes reexamination filed on or after September 16, 2012. See 37 CFR 1.913(b). Guidance on the former practice is available in revision 07.2022 of the 9 th Edition of the MPEP.
The Office does not accept requests for inter partes reexamination filed on or after September 16, 2012. See 37 CFR 1.913(b). Guidance on the former practice is available in revision 07.2022 of the 9 th Edition of the MPEP.
Citations
| Primary topic | Citation |
|---|---|
| AIA Effective Dates | 37 CFR § 1.913(b) |
Source Text from USPTO’s MPEP
This is an exact copy of the MPEP from the USPTO. It is here for your reference to see the section in context.
Official MPEP § 2692 — Distribution of Certificate
Source: USPTO2692 Distribution of Certificate [R-01.2024]
The Office does not accept requests for inter partes reexamination filed on or after September 16, 2012. See 37 CFR 1.913(b). Guidance on the former practice is available in revision 07.2022 of the 9th Edition of the MPEP.